Comparison Analysis of Bore Pile Foundations and Piles to Time and Cost of Construction in Tanjung Perak Sea Keeping Base and Class II Beach Construction Project

Authors

  • Alifiandi Varian Universitas 17 Agustus 1945 Surabaya
  • Putri Suci Mawariza Universitas 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.30736/cvl.v8i2.1099

Keywords:

Bore Pile, Cost, Pile, Time

Abstract

In this project using a pile foundation, but during the foundation work there were several obstacles, namely hydraulic tools that were still not ready to use, hydraulic tool repairs, and piles that were one week late, causing delays in foundation work.Therefore workers cannot work optimally while waiting for the tools to arrive. In addition to delays, there are also cost overruns where workers are still being paid for work that is not optimal, so it is necessary to compare these foundations with other foundations in order to find differences in foundations that are more efficient and minimize the problems that have occurred. From the results of data processing, it can be seen that the duration of time required for the preparatory work to the 30x30cm pile foundation with a depth of 16m for 65 points on the class 2 marine and beach guard base of Tanjung Perak is 56 days and requires a fee of IDR 655,305,366.00. For the duration of the preparatory work up to the 30cm bore pile foundation with a depth of 16m as many as 65 points on the class 2 marine and beach guard base Tanjung Perak is 59 days and requires a fee of IDR 520,779,603.00. Then the difference in time between the pile foundation and the bore pile foundation is 12 days. The pile foundation can save as much as 21.4% or 12 days of time from the bore pile foundation.

Downloads

Download data is not yet available.

References

N. AL-Rousan, N. A. Mat Isa, and M. K. Mat Desa, “Efficient single and dual axis solar tracking system controllers based on adaptive neural fuzzy inference system,” J. King Saud Univ. - Eng. Sci., vol. 32, no. 7, pp. 459–469, 2020, doi: 10.1016/j.jksues.2020.04.004.

Ariany Frederika, A.A Wiranata, and Kadek Riska Larasati, “Perbandingan Biaya dan Waktu Pelaksanaan Pekerjaan Balok Struktur Beton Gedung antara Metode Konvensional dengan Precast (Studi Kasus: Grand Whiz Hotel, Gatot Subroto Barat),” J. Ilm. Tek. Sipil, vol. 18, no. 2, pp. 1–8, 2014.

M. Muluk, D. Hamid, S. Satwarnirat, D. Dalrino, and M. Santi, “Studi Perbandingan Pondasi Tiang Pancang Dengan Pondasi Bore Pile (Studi Kasus: Pelaksanaan Pembangunan Pondasi Tower Grand Kamala Lagoon-Bekasi),” J. Tek. Sipil ITP, vol. 7, no. 1, pp. 26–33, 2020, doi: 10.21063/jts.2019.v701.04.

H. Mousazadeh, A. Keyhani, A. Javadi, H. Mobli, K. Abrinia, and A. Sharifi, “A review of principle and sun-tracking methods for maximizing solar systems output,” Renew. Sustain. Energy Rev., vol. 13, no. 8, pp. 1800–1818, 2009, doi: 10.1016/j.rser.2009.01.022.

C. E. Kusuma and F. Lestari, “Perhitungan Daya Dukung Tiang Pancang Proyek Penambahan Line Conveyor Batubara,” J. Tek. sipil, vol. 02, no. 01, pp. 1–7, 2021, [Online]. Available: http://jim.teknokrat.ac.id/index.php/tekniksipil/article/view/798

H. S. D. Roring and F. Moniaga, “ESTIMASI DURASI PROYEK KONSTRUKSI GEDUNG DENGAN MICROSOFT PROJECT PADA PERENCANAAN GEDUNG TOURISM INFORMATION CENTRE TOMOHON,” vol. 17, no. 1, pp. 12–17, 2021.

I. Abadi, A. Soeprijanto, and A. Musyafa’, “Extreme learning machine approach to estimate hourly solar radiation on horizontal surface (PV) in Surabaya -East java,” 2014 1st Int. Conf. Inf. Technol. Comput. Electr. Eng. Green Technol. Its Appl. a Better Futur. ICITACEE 2014 - Proc., pp. 372–376, 2015, doi: 10.1109/ICITACEE.2014.7065774.

J. Pengabdian, S. Anwar, and M. Hospital, “Metode Pelaksanaan Pekerjaan Pondasi Bore Pile Pada proyek Gedung Baru Instalasi Pelayanan Utama Rumah Sakit Dr Saiful Anwar Malang Methods for Bore Pile Foundation Work in the New Main Service Installation Building project at,” vol. 3, no. 2002, pp. 16–25, 2023.

A. Awasthi, A. K. Shukla, M. M. Sr, C. Dondariya, and K. N. Shukla, “Machine Translated by Google Laporan Energi Ulasan tentang teknologi pelacakan matahari dalam sistem PV surya Machine Translated by Google,” vol. 6, pp. 392–405, 2020.

F. Zulkarnain, “Pengembangan Dan Analisis Campuran Beton Mutu Tinggi Untuk Struktur Dermaga Di Indonesia,” SiNTESa CERED Semin. Nas. Teknol. Edukasi dan Hum., vol. 2021, pp. 54–58, 2021.

A. Karafil, H. Ozbay, M. Kesler, and H. Parmaksiz, “Calculation of optimum fixed tilt angle of PV panels depending on solar angles and comparison of the results with experimental study conducted in summer in Bilecik, Turkey,” ELECO 2015 - 9th Int. Conf. Electr. Electron. Eng., no. November 2015, pp. 971–976, 2016, doi: 10.1109/ELECO.2015.7394517.

A. Maulidi, S. Arifin, and H. Suyoso, “Penjadwalan Proyek Konstruksi Menggunakan Critical Path Method (Studi Kasus: Gedung Laboratorium Terpadu Fakultas Teknik Universitas Jember),” J. Ilm. MITSU, vol. 9, no. 1, pp. 1–8, 2021, doi: 10.24929/ft.v9i1.992.

I Wayan Jawat, Putu Panji Tresna Gita, and I Made Satria Dharmayoga, “Kajian Metoda Pelaksanaan Pekerjaan Pondasi Bored Pile Pada Tahap Perencanaan Pelaksanaan,” Padur. J. Tek. Sipil Univ. Warmadewa, vol. 9, no. 2, pp. 126–142, 2020, doi: 10.22225/pd.9.2.1830.126-142.

D. Khomsiati, Nur Latifah, “Perbandingan Daya Dukung Aksial Pondasi Tiang Bor Tunggal Menggunakan Data Standard Penetration Test (SPT) dan Pile Driving Analizer (PDA) Test pada Proyek Pembangunan Jalan Tol Pandaan Malang,” J. Bangunan, vol. 24, no. 1, pp. 25–32, 2019.

L. Nias-barat, Y. Y. P. Gulo, and K. I. Sari, “Evaluasi Perencanaan Pondasi Sumuran Pada Jembatan Bo’u Lahomi Nias-Barat,” vol. 7, no. 1, 2023.

M. R. Asmoro and A. Setiyono, “Analisis Antara Penggunaan Pondasi Bore Pile dengan Tiang Pancang (Studi Kasus: Gedung DPRD Kota Surabaya),” … Keinsinyuran Progr. Stud. …, pp. 774–780, 2021, [Online]. Available: http://research-report.umm.ac.id/index.php/SKPSPPI/article/view/4369

A. K. Umam, S. Winarto, A. Ridwan, and A. I. Candra, “Perencanaan Pondasi Tiang Pancang Gedung Dinas Tenaga Kerja Dan Transmigrasi,” J. Manaj. Teknol. Tek. Sipil, vol. 3, no. 1, p. 23, 2020, doi: 10.30737/jurmateks.v3i1.883.

M. Sabir, “Optimization of PID Controller Based on PSO for Photovoltaic Dual Axis Solar Tracking in Gresik Location-East... ali musyafa Related papers Opt imal PID cont roller design t hrough swarm int elligence algorit hms for sun t racking syst em A Novel Open-Loo,” 2016.

M. Sahar, G. Tampubolon, and A. Gunawan, “Sistem Monitoring Lingkungan Pada Pembangkit Listrik Tenaga Surya Berbasis Singkatan dari Supervisory Control And Data Acquisition,” J. Karya Ilm. Multidisiplin, vol. 2, no. 1, pp. 106–115, 2022, doi: 10.31849/jurkim.v2i1.9208.

A. B. Pulungan, Q. Fajri, and I. Yelfianhar, “Peningkatan Daya Keluaran Panel Surya Menggunakan Single Axis Tracker Pada Daerah Khatulistiwa,” JTEV (Jurnal Tek. Elektro dan Vokasional), vol. 7, no. 2, p. 261, 2021, doi: 10.24036/jtev.v7i2.113304.

Downloads

PlumX Metrics

Published

2023-09-15

How to Cite

Varian, A., & Mawariza, P. S. (2023). Comparison Analysis of Bore Pile Foundations and Piles to Time and Cost of Construction in Tanjung Perak Sea Keeping Base and Class II Beach Construction Project. Civilla : Jurnal Teknik Sipil Universitas Islam Lamongan, 8(2), 137–144. https://doi.org/10.30736/cvl.v8i2.1099

Issue

Section

Jurnal CIVILA