Cost and Time Comparison Analysis Using Microsoft Project (Case Study: Phase VII Work of the Surabaya Tanjung Perak Berlian Pier Structure Strengthening Project)
DOI:
https://doi.org/10.30736/cvl.v8i2.1110Keywords:
CPM, Microsoft Project, RAB ReschedulingAbstract
Sometimes the execution of a project does not proceed smoothly because there are barriers that impede the present work. Uncertain weather conditions are one of the most common challenges encountered in the field during the Tanjung Perak Diamond Pier Structure Strengthening project in Surabaya. This is because the initial planning did not account for the weather conditions that would occur during the project's implementation. As a result, rescheduling is carried out to generate a reasonable and realistic timetable. Many strategies are employed in scheduling, with the expectation that the method will help in planning and scheduling. The goal of this research is to determine the time necessary for project implementation after rescheduling. This research is analytical in character. Secondary data, such as schedules and Budget Plans (RAB), are collected by directly requesting the necessary data from related parties, then evaluating the initial schedule, and finally preparing a new schedule using Microsoft Project tools and the Critical Path Method (CPM). The results of this study obtained a rescheduling duration of 99 days, 22 days faster than the actual planned duration of 121 days, and a fee of IDR. 28,535,441,605 of the initial planned cost of IDR. 35,017,986,296.10.
Downloads
References
Aslam, & T.M Kamaludin, View of Rescheduling the Palu V Bridge Construction Project Using Microsoft Project, 2021.
Beatrix, M., Lukmansyah, I., Oskar, D., & Muin, E. A, Analisa Metode Critical Path Methodpada Proyek Pembangunan Elyon Christian School S Urabaya. In MITSU" Media Informasi Teknik Sipil UNIJA (Vol. 7, Issue 2), 2019.
Ervianto, W.I. 2018. Teori Aplikasi Manajemen Proyek Konstruksi. Salemba Empat. Yogyakarta
Han-Seong Gwak, Sang-Hyuk Son, Young-Jun P, & Dong-Eun Lee, Exact Time-Cost Tradeoff, 2016.
Ilwaru, V. Y. I., Rahakbauw, D. L., & Tetimelay, J, Penjadwalan Waktu Proyek Pembangunan Rumah dengan Menggunakan CPM (Critical Path Method), 2018.
I put Dody Lesmana.& Elly Antika, Manajemen Proyek dengan Scrum, CV. Absolute Media, 2019.
Marina & Retna Hapsari Kartadipura, Pondok Darul Hijrah Putera Martapura, 2021
Maulidi, A., Arifin, S., & Suyoso, D. H, Penjadwalan Proyek Konstruksi Menggunakan Critical Path Method (Stusi Kasus: Gedung Laboratorium Terpadu Fakultas Teknik Universitas Jember). In MITSU" Media Informasi Teknik Sipil UNIJA (Vol. 9, Issue 1), 2021.
Nurhayati, Manajemen Proyek. Cetakan Pertama, Graha Ilmu, Yogyakarta, 2020.
Onur, D & C. Stoy, Conceptual Estimation of Construction Costs Using the Multistep Ahead Approach, 2016.
Ramdhani, Fitra, Analisis Biaya dan Waktu dengan Metode Earned Value Concept Pada Proyek BJDM Area RL Construction At Well 32-21B Area 9 PT. Adhi Karya CS Work Unit Rate Pacagea-Duri. Jurnal Ilmiah, Fakultas, 2016.
Teknik Universitas Abdurrab, Pekanbaru.Rizky, F. M., & Nugraheni, F, Analisis Penjadwalan Ulang (Reschedulling) Proyek Masjid Muhammad Ali Al-Hind As- Syahiyarhamuhullah dengan Metode Precedence Diagram Method, 2019.
Santoso, A, Analisis Percepatan Pelaksanaan Pekerjaan Proyek Menggunakan Critical Path Method (Studi Kasus Pembangunan Pasar Baru Kota Probolinggo), 2019.
Siswanto, Pengantar Manajemen. Jakarta: Bumi Aksara, 2019.
Soehendradjati, RJB., Draft kuliah : Manajemen Kontruksi, Jurusan Teknik Sipil, Universitas Gadjah Mada, Yogyakarta, 2019.
Umbu, F., Dappa, L., Sari, S. N., & Hermawan, A, Analisis Penjadwalan Waktu Menggunakan Metode CPM (Studi Kasus : Proyek Pembangunan Gedung SMP Negeri 3 Saptosari, Gunung Kidul, Yogyakarta). EQUILIB, 03(01), 35–44, 2022.
Utomo, F. P, Penjadwalan Ulang Proyek Konstruksi Menggunakan Metode PDM dan CPM (Studi Kasus Pada Pembangunan Toserba Yogya di Pekalongan). In UJM (Vol. 10, Issue 1). http://journal.unnes.ac.id/sju/index.php/ujm, 2021.
Virginia M. Sorongan, Ariestides K. T, Dundu, Jermias Tjakra, Analisa Penjadwalan Proyek Menggunakan Metode PDM Dengan Menggunakan Konsep Cadangan Waktu Pada Proyek Peningkatan Ruas Jalan Tondano-Kembes-Manado Seksi 2, 2022.
Widiasanti, Irika dan Lenggogeni, Manajemen konstruksi. Bandung: PT Remaja Rosdakarya, 2013.
Y. Rahmat Akbar, Mar’aini, Penentuan Jalur Kritis untuk Manajemen Proyek ( Studi Kasus Pembangunan Jalan Selensen – Kota Baru – Bagan Jaya), 2022.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 Mohammad Rizal Mantovani, Michella Beatrix
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish in this journal agree to the following terms:
-
- Copyright on any article is held by the author.
- The author grants the journal first publication rights with the work licensed concurrently under a Creative Commons Attribution License that allows others to share the work with an acknowledgment of authorship and initial publication of the work in this journal.
- Authors may make separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of that journal (for example, posting it to an institutional repository or publishing it in a book), with an acknowledgment of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (for example, in an institutional repository or on their website) before and during the submission process, as doing so can lead to productive exchange, as well as earlier and greater citation of the published work.
- Published articles and related materials distributed under a Creative Commons Attribution-ShareAlike 4.0 International License
Civilla (Jurnal Teknik Sipil Universitas Islam Lamongan) by Universitas Islam Lamongan is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Based on a work at https://jurnalteknik.unisla.ac.id/index.php/CVL/index