Penentuan Kapasitas PMT SF6 Pada Bus 70 KV Menggunakan Simulasi Program ETAP

Authors

  • Jeri Widianto Prodi Teknik Elektro Universitas Singaperbangsa Karawang
  • Rahmat Hidayat Prodi Teknik Elektro Universitas Singaperbangsa Karawang
  • Arief Budi Laksono Teknik Elektro Universitas Islam Lamongan

DOI:

https://doi.org/10.30736/je-unisla.v6i2.694

Keywords:

Substation, Voltage Breaker (PMT) SF6, Bus 70KV Short Circuit Current, ETAP program.

Abstract

The electric power system consists of several components, namely generation, distribution, transmission and load. Along with the rapid development of technology in the field of electricity today, a protection system is installed at substations, one of which is a power
breaker (PMT) at each substation. In the event of a disturbance, the protection relay will detect and instruct the breaker to open or disconnect the circuit from the disturbance, then a circuit breaker will receive a signal from the relay and in the end will decide the circuit according to
its current rating. Based on the type of PMT isolation media, PMT is divided into 4 types, one of which is the SF6 gas isolation media type. This type of PMT can be used to cut currents up to 40 KA and in circuits with a voltage of 765 KV. It must be noted that if the current is very large at the time of short circuit, then the thing that must be considered is the capacity of the
breaker itself. To determine the breaker capacity, it is sought from the largest short-circuit current, namely a three-phase short circuit. In finding a three-phase short circuit current can be simulated using the ETAP (Electric Transient Analysis Program) program. ETAP can simulate
power flow and short circuit current. The results of the calculation of the PMT capacity on the 70 KV bus are 0.324 KA and from the results of the calculation and analysis of the PMT it is included in the rating of 12.5 KA where the PMT with the rating value can decide the fault current from 0.9 KA -7.74 KA

Downloads

Download data is not yet available.

References

Bonggas L. Tobing. 2003. Peralatan Tegangan Tinggi. Jakarta : PT Gramedia Pustaka Utama

Hendra, E. Lazuardi, M. Suparlan. 2015. Studi Penentuan Kapasitas Pemutus Tenaga Sisi 20 KV Pada Gardu Induk Sekayu,

Mikrotiga Vol 2, No. 1, Januari 2015.

LSTDE UNAND. 2013. Tentang ETAP (Electric Transient and Analysis Program) Power Station. Padang : http://stdelaboratory.blogspot.com/2013/11/ tentang-etap-electric-transient- and.html (diakses 24 Maret 2020).

PERUM JASA TIRTA II. 2002. PEDOMAN OPERASI DAN PEMELIHARAAN PEMBANGKIT LISTRIK TENAGA AIR Ir.H.DJUANDA. Purwakarta : PERUM JASA TIRTA II

PT PLN. 2014. Buku Pedoman Pemeliharaan PEMUTUS TENAGA. Jakarta : PT PLN

Stevenson William D,1994. Analisa Sistem Tenaga Listrik. Jakarta: Gelora Aksara Pratama.

PT PLN. Proteksi Sistem Penyaluran. Bogor : PT PLN

PlumX Metrics

Published

20-09-2021

How to Cite

Widianto, J., Hidayat, R., & Laksono, A. B. (2021). Penentuan Kapasitas PMT SF6 Pada Bus 70 KV Menggunakan Simulasi Program ETAP. JE-Unisla, 6(2), 35–40. https://doi.org/10.30736/je-unisla.v6i2.694

Issue

Section

editorial elektro

Most read articles by the same author(s)