Analysis Of Supply Chain Management Effectiveness in Improving Project Time and Cost Performance Through Digitalism Supply Chain Management

Authors

  • Ely Mulyati, S.T., M.T. Bina Darma University
  • Muhammad Wahyu Desriandi Bina Darma University

DOI:

https://doi.org/10.30736/cvl.v11i2.1743

Keywords:

Supply Chain Management, Digitalism SCM, Smart-GEP, ERP, IOG E-Commerce, Project Performance, Time and Cost Performance

Abstract

The increasing complexity of oil and gas construction projects requires effective Supply Chain Management (SCM) supported by digital integration to achieve efficient schedule and cost performance. This study aims to analyze the effectiveness of SCM and Digital Supply Chain Management (DSCM) in the Demineralized Facility Construction Project at Company ABC. A quantitative approach was employed using purposive sampling involving 58 respondents engaged in supply chain, procurement, engineering, logistics, project management, and contractor activities. Primary data were collected through a structured five-point Likert-scale questionnaire and analyzed using IBM SPSS Statistics 31 through validity, reliability, multicollinearity, descriptive, and multiple linear regression analyses. The independent variables comprised SCM practices and DSCM implementation through Smart-GEP, Enterprise Resource Planning (ERP), and IOG E-Commerce, while the dependent variable was project performance, measured through schedule and cost performance. The regression model was statistically significant (F = 107.953, p < 0.001) and explained 79.7% of the variation in project performance (R² = 0.797). DSCM showed a significant positive effect on project performance, demonstrating that integrated digital platforms strengthen procurement transparency, information integration, real-time monitoring, and project coordination. These findings emphasize the strategic contribution of DSCM to schedule and cost performance in oil and gas construction projects.

Downloads

Download data is not yet available.

Author Biographies

Ely Mulyati, S.T., M.T., Bina Darma University

Civil Engineering Department

Muhammad Wahyu Desriandi, Bina Darma University

Civil Engineering Department

References

[1] S. Chopra, P. Meind, and D. V. Kalra, Supply Chain Management : Strategy, Planning, and Operation (6th Edition). 2016.

[2] R. Cooper, Supply Chain Development for the Lean Enterprise: Interorganizational Cost Management. Routledge, 2017.

[3] S. Demirkesen and B. Ozorhon, “Impact of Integration Management on Construction Project Management Performance,” Int. J. Proj. Manag., vol. 35, no. 8, pp. 1639–1654, 2017.

[4] S. I. Sabilla, R. Sarno, and Y. A. Effendi, “Optimizing Time and Cost Using Goal Programming and FMS Scheduling,” in 2018 International Conference on Information and Communications Technology, ICOIACT 2018, 2018, pp. 244 – 249. doi: 10.1109/ICOIACT.2018.8350727.

[5] M. A. P. Subali, R. Sarno, and Y. A. Effendi, “Time and Cost Optimization Using Fuzzy Goal Programming,” in 2018 International Conference on Information and Communications Technology, ICOIACT 2018, 2018, pp. 471 – 476. doi: 10.1109/ICOIACT.2018.8350723.

[6] L. Friescilia and O. Gondokusumo, “Implementing Three-Variance Approach for Project Time and Cost Control in a Building Construction Project (Case Study: A Project in West Java),” in IOP Conference Series: Materials Science and Engineering, 2019. doi: 10.1088/1757-899X/650/1/012010.

[7] B. Ageron, O. Bentahar, A. Gunasekaran, and O. Bentahar, “Digital Supply Chain : Challenges And Future Directions,” Supply Chain Forum An Int. J., vol. 21, no. 3, pp. 133–138, 2020, doi: 10.1080/16258312.2020.1816361.

[8] B. Farrington and K. Lysons, Procurement and Supply Chain Management. Pearson UK, 2020.

[9] A. Herzanita, “Implementation of Standardized WBS (Work Breakdown Structure) for Time And Cost Performance. (Study Case: Building Project PT. X, Kuala Tanjung, Sumatera Utara),” in IOP Conference Series: Materials Science and Engineering, 2019. doi: 10.1088/1757-899X/508/1/012049.

[10] S. Riazi, M. Riazi, M. Nasrun, M. Nawi, and M. F. Abu, “Developing A Holistic Project Time Management Framework Utilizing Fundamental Supply Chain Management ( SCM ) Tools to Overcome Delay in Malaysian Public Sector Building Projects,” vol. 11, no. 1, pp. 31–41, 2020.

[11] H. Jukka, I. Mika, and B. Saara, “Digitalizing Procurement : The Impact Of Data Analytics On Supply Chain Performance,” 2021, doi: 10.1108/SCM-05-2020-0201.

[12] X. Wei, V. Prybutok, and B. Sauser, “Review of Supply Chain Management Within Project Management,” Proj. Leadersh. Soc., vol. 2, p. 100013, 2021.

[13] G. Dharmana, D. W. I. Santika, K. Pendidikan, R. Dan, P. N. Bali, and J. T. Sipil, “Analisis Kinerja Supply Chain Management Terhadap Efisiensi Biaya Dan Waktu Pekerjaan Struktur Proyek Pembangunan Smpn 5 Abiansemal,” 2023.

[14] S. Aziz, P. Kumar, and A. B. Khan, “Assessing the Impact of Digital Supply Chain Management on the Sustainability of Construction Projects,” vol. 24, no. 045, pp. 60–73, 2024, doi: 10.26794/2308-944X-2024-12-3-60-73.

[15] A. Hasibuan et al., “Performance Analysis of Supply Chain Management with Supply Chain Operation Reference Model”.

[16] A. I. Yunus et al., Manajemen Proyek. CV. Gita Lentera, 2024.

[17] M. G. Akbar and E. Mulyati, “Pengendalian Biaya dan Waktu dengan Metode Earned Value Analysis (EVA) pada Proyek Jaringan Ipal Kota Palembang,” J. Tek. Sipil dan Teknol. Konstr., vol. 10, no. 2, 2024.

[18] D. D. G. Pangemanan, E. Aprianti, and F. A. Larwuy, “Time and Cost Optimization of the Coordinating Ministry 4 Office Building Construction in Nusantara Using the Time-Cost Trade-Off Method,” Eng. Technol. Appl. Sci. Res., vol. 15, no. 6, pp. 28622 – 28628, 2025, doi: 10.48084/etasr.11842.

[19] G. Zenezini, G. E. C. Bolivar, and T. Ekhlasi, “The Impact of Integrated Supply Chain Platforms on Project Management Criteria : A Study of Time, Cost, Risk Management in Construction Projects,” 2024.

[20] F. Rachim, “Study on the Optimization of Implementation Time for the Construction of the Baraka Sports Facility Center ( APBD PEN ) Kab . Enrekang South Sulawesi,” vol. 09, no. 2, pp. 119–124, 2024.

Downloads

Published

2026-09-17

How to Cite

Mulyati, E., & Desriandi, M. W. (2026). Analysis Of Supply Chain Management Effectiveness in Improving Project Time and Cost Performance Through Digitalism Supply Chain Management. Civilla : Jurnal Teknik Sipil Universitas Islam Lamongan, 11(2), 176–187. https://doi.org/10.30736/cvl.v11i2.1743

Issue

Section

Jurnal CIVILA

Similar Articles

1 2 3 4 5 > >> 

You may also start an advanced similarity search for this article.