Application Of Crashing Method On Sutt Construction Project 150 Kv Kolaka - Pomalaa Switching - PT Antam Pomalaa Customer
DOI:
https://doi.org/10.30736/cvl.v10i2.1443Keywords:
Crashing Method, Ontrack, Critical Trajectory, Tower, OptimalAbstract
Construction projects often experience delays that can result in a fine of 1/1000 of the contract value according to Presidential Regulation No. 54/2010. To overcome this, the crashing program method can be applied to accelerate the project duration by identifying and compressing the critical path. The case study on the 150 kV Kolaka - Pomalaa Switching - PT Antam Pomalaa SUTT Construction Project which experienced delays, analyzed the need for additional time, equipment and labor. With an initial contract duration of 300 calendar days, the implementation of the crashing program focused on four priority segments of work (TIP 40-54, TIP 01-11, TIP 23-40, and TIP 11-23). The results of the analysis showed that the application of the crashing program method successfully optimized the project completion duration to 263 days, allowing the project to return to the contract schedule and avoid potential fines.
Downloads
References
F. R. G. PERKASA, “THE EFFECT OF THE IMPLEMENTATION OF CORPORATE SOCIAL RESPONSIBILITY (CSR) ON COMPANY IMAGE (Study Case in State Owned Companies in Indonesia Using CSR Disclosure Index from 2015-2020).” Universitas Islam Indonesia, 2023.
E. A. Djamhari et al., “Tracking Financing Footprints: Environmental and Social Impacts of the Nickel Industry in Indonesia,” https://repository. theprakarsa. org/, 2024.
C. Medina, C. R. M. Ana, and G. González, “Transmission grids to foster high penetration of large-scale variable renewable energy sources–A review of challenges, problems, and solutions,” Int. J. Renew. Energy Res., vol. 12, no. 1, pp. 146–169, 2022.
B. T. YALEM, “OPTIMIZING PROJECT CRASHING TIME USING LINEAR PROGRAMMING APPROACH: ACASE STUDYOF DEBRE MARKOSTOWN.” 2021.
C. Ou-Yang and W.-L. Chen, “A hybrid approach for project crashing optimization strategy with risk consideration: a case study for an EPC project,” Math. Probl. Eng., vol. 2019, no. 1, p. 9649632, 2019.
N. Noviandi, “Optimalisasi Pelaksanaan Proyek Dengan Metode Crashing Menggunakan Software Microsoft Project (Studi Kasus: Proyek Pengadaan Pembangunan Baru Ruang Isolasi Bertekanan Negatif).” Universitas Islam Riau, 2022.
M. B. Firdaus, H. T. Tjendani, and B. Witjaksana, “Acceleration Analysis Using the Crashing Method in the Sdn Kutisari 2 Development Project,” Int. J. Adv. Technol. Eng. Inf. Syst., vol. 2, no. 4, pp. 366–375, 2023.
L. A. Kweek and P. Arumsari, “Acceleration Alternatives Cost Analysis of Train Station Construction Project,” in IOP Conference Series: Earth and Environmental Science, IOP Publishing, 2025, p. 12045.
C. R. Heffi, H. Lukman, and S. AM, “DETERMINANTS OF POVERTY ON SUMATERA DYNAMIC PANEL DATA ANALYSIS,” DETERMINANTS OF POVERTY ON SUMATERA DYNAMIC PANEL DATA ANALYSIS. ICBASL 2019, 2019.
A. P. GRANT, A. CO-FINANCING, and P. T. P. L. NEGARA, “FOR OFFICIAL USE ONLY,” Energy, 2023.
E. Matthes, Python crash course: A hands-on, project-based introduction to programming. no starch press, 2023.
E. N. N. Okiti, “Influence of Office Application Packages on Entrepreneurial Intentions and Skill Acquisition of Office Technology and Management Students in Public Polytechnics.” Kwara State University (Nigeria), 2023.
H. M. Mohamad, M. I. Mohamad, I. Saad, N. Bolong, J. Mustazama, and S. N. M. Razali, “A case study of s-curve analysis: Causes, effects, tracing and monitoring project extension of time,” Civ. Eng. J., vol. 7, no. 4, pp. 649–661, 2021.
H. N. Yaqin, H. T. Tjendani, and B. Witjaksana, “Analysis of The Acceleration of Time and Cost of Implementing Building Construction Projects Using The Critical Path Method (CPM) Method,” Devot. J. Res. Community Serv., vol. 4, no. 2, pp. 336–346, 2023.
S. P. Mukherjee, A guide to research methodology: An overview of research problems, tasks and methods. CRC Press, 2019.
M. Baimyrzaeva, “Beginners’ guide for applied research process: What is it, and why and how to do it,” Univ. Cent. Asia, vol. 4, no. 8, pp. 1–42, 2018.
S. Abutabenjeh and R. Jaradat, “Clarification of research design, research methods, and research methodology: A guide for public administration researchers and practitioners,” Teach. public Adm., vol. 36, no. 3, pp. 237–258, 2018.
C. P. Wheater, J. R. Bell, and P. A. Cook, Practical field ecology: a project guide. John Wiley & Sons, 2020.
H. Taherdoost, “Data collection methods and tools for research; a step-by-step guide to choose data collection technique for academic and business research projects,” Int. J. Acad. Res. Manag., vol. 10, no. 1, pp. 10–38, 2021.
Z. C. Chan, Y. Fung, and W. Chien, “Bracketing in phenomenology: Only undertaken in the data collection and analysis process,” Qual. Rep., vol. 18, no. 30, pp. 1–9, 2013.
S. S. Manvi and G. K. Shyam, “Resource management for Infrastructure as a Service (IaaS) in cloud computing: A survey,” J. Netw. Comput. Appl., vol. 41, pp. 424–440, 2014.
S. R. Duea, E. B. Zimmerman, L. M. Vaughn, S. Dias, and J. Harris, “A guide to selecting participatory research methods based on project and partnership goals,” J. Particip. Res. Methods, vol. 3, no. 1, pp. 10–35844, 2022.
D. D. Alem, “An overview of data analysis and interpretations in research,” Int. J. Acad. Res. Educ. Rev., vol. 8, no. 1, pp. 1–27, 2020.
S. A. Mazhar, R. Anjum, A. I. Anwar, and A. A. Khan, “Methods of data collection: A fundamental tool of research,” J. Integr. Community Heal., vol. 10, no. 1, pp. 6–10, 2021.
B. T. Khoa, B. P. Hung, and M. Hejsalem-Brahmi, “Qualitative research in social sciences: data collection, data analysis and report writing,” Int. J. Public Sect. Perform. Manag., vol. 12, no. 1–2, pp. 187–209, 2023.
I. Karunarathna, P. Gunasena, T. Hapuarachchi, and S. Gunathilake, “The crucial role of data collection in research: Techniques, challenges, and best practices,” Uva Clin. Res., pp. 1–24, 2024.
C. Cardno, “Policy Document Analysis: A practical educational leadership tool and a qualitative research method.,” Educ. Adm. Theory Pract., vol. 24, no. 4, pp. 623–640, 2018.
H. Kerzner, Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons, 2025.
R. Kazaryan, D. Pogodin, and A. Shatrova, “Aspects of scheduling processes and results of the reorganization of projects in high-rise construction objects,” in E3S Web of Conferences, EDP Sciences, 2019, p. 4002.
S. A. Mubarak, Construction project scheduling and control. John Wiley & Sons, 2015.
A. K. Mishra, “Implication of theory of constraints in project management,” Int. J. Adv. Trends Eng. Technol., vol. 5, no. 1, pp. 1–13, 2020.
D. E. Nopriyanto, E. Wulandari, and L. D. Nugroho, “Analysis of Delays in Construction Time of the Banjarsari Water Gate Project, Sidoarjo District Using Critical Path Method,” Enrich. J. Multidiscip. Res. Dev., vol. 3, no. 1, pp. 26–38, 2025.
S. Zareei, “Project scheduling for constructing biogas plant using critical path method,” Renew. Sustain. Energy Rev., vol. 81, pp. 756–759, 2018.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Fatmawaty Rachim, Frans Ryanto Hasudungan Tampubolon, Herwina Rahayu Putri, Andi Butsainah Tumaadir

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish in this journal agree to the following terms:
-
- Copyright on any article is held by the author.
- The author grants the journal first publication rights with the work licensed concurrently under a Creative Commons Attribution License that allows others to share the work with an acknowledgment of authorship and initial publication of the work in this journal.
- Authors may make separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of that journal (for example, posting it to an institutional repository or publishing it in a book), with an acknowledgment of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (for example, in an institutional repository or on their website) before and during the submission process, as doing so can lead to productive exchange, as well as earlier and greater citation of the published work.
- Published articles and related materials distributed under a Creative Commons Attribution-ShareAlike 4.0 International License
Civilla (Jurnal Teknik Sipil Universitas Islam Lamongan) by Universitas Islam Lamongan is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Based on a work at https://jurnalteknik.unisla.ac.id/index.php/CVL/index